Development Permit Details
14 108903 00 PC
- Number
- 14 108903 00 PC
- Type
- Public Construction - PW - Utility/Street - Water
- Status
- Completed
- Details
- KUEBLER GATEWAY SUBDIVISION - 2531 BOONE RD SE PN 715714
- Description
- PUBLIC INFRASTRUCTURE FOR THE PROPOSED SUBDIVISION. 7.32 ACRES TOTAL, BUT SDF ALREADY PAID ON LOTS 5 AND 6 WITH THEIR DEVELOPMENT. LJM
Person Details
JOSH WELLS
- Roles
- Engineer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
K AND E EXCAVATING
- Roles
- Contractor
- Address
-
3871 LANGLEY ST SE
SALEM OR 97317-9322
Property Details
Action Details
Agreements
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 8/17/2015
- Assigned Staff:
- Lyle Misbach
- View Details
Info
Application Intake
-
Assign Bin Number
- Status:
- Complete
- Completed Date:
- 5/20/2014
- Assigned Staff:
- PW Coordinator
- View Details
-
Make Ready To Issue (DS)
- Status:
- Approved
- Completed Date:
- 11/24/2015
- Assigned Staff:
- Lyle Misbach
- View Details
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 7/2/2015
- Assigned Staff:
- Lyle Misbach
- View Details
-
Engineering Review
- Status:
- Complete - No Redlines
- Completed Date:
- 7/1/2015
- Assigned Staff:
- Don Whitehurst
- View Details
-
Operations Review
- Status:
- Complete - No Redlines
- Completed Date:
- 6/26/2015
- Assigned Staff:
- PW Water Group
- View Details
-
Traffic Review
- Status:
- Complete - No Redlines
- Completed Date:
- 6/26/2015
- Assigned Staff:
- Tony Martin
- View Details
-
Erosion Control Review
- Status:
- Complete - No Redlines
- Completed Date:
- 7/1/2015
- Assigned Staff:
- Andy Groh
- View Details
-
Fire Review
- Status:
- Approved
- Completed Date:
- 7/1/2015
- Assigned Staff:
- John Stroebel
- View Details
Info
PW Inspections
-
As-Built Review
- Status:
- Complete
- Completed Date:
- 3/15/2016
- Assigned Staff:
- Suzanne Keller
- View Details
-
Acceptance
- Status:
- Accepted
- Completed Date:
- 2/25/2015
- Assigned Staff:
- PW Engineering
- View Details
-
10-month TV Inspection
- Status:
- Approved
- Completed Date:
- 11/28/2016
- Assigned Staff:
- PW Sewer
- View Details
-
10 month warranty inspection
- Status:
- Approved
- Completed Date:
- 11/28/2016
- Assigned Staff:
- PW Inspector
- View Details
-
Erosion Control Inspection
- Status:
- Approved
- Completed Date:
- 3/15/2016
- Assigned Staff:
- PW Inspector
- View Details
Info
PW Water Inspections
-
Chlorination <=12"
- Status:
- Completed by City
- Completed Date:
- 2/18/2016
- Assigned Staff:
- Donald Lovas
- View Details
-
Water Tap Installation
- Status:
- Completed by City
- Completed Date:
- 3/15/2016
- Assigned Staff:
- William Swint
- View Details
Info