Comment Number Scheduled Date Comment Date Staff Result Comment
1 11/25/2015 James Suing Reopened See Revision/Addendum 01
2 11/25/2015 James Suing Reopened See Revision/Addendum 02
3 11/30/2015 11/30/2015 Rex Amstutz In Compliance NOT STARTED
4 12/14/2015 12/14/2015 Rex Amstutz In Compliance JUST GETTING STARTED ON INSTALLING BMPS, NO EROSION ISSUES
5 12/29/2015 12/29/2015 Rex Amstutz In Compliance CREW ON HOLIDAY, SITE NOT ACTIVE
6 1/13/2016 1/13/2016 Rex Amstutz In Compliance NO EROSION ISSUES
7 2/1/2016 1/28/2016 Rex Amstutz In Compliance LAYING LAST COUPLE OF STI CK OF PIPE AND WILL START LANDSCAPING THE SITE FOR COMPLETION
8 2/16/2016 2/16/2016 Rex Amstutz In Compliance CREW PULLED OFF SITE, STRAW LAYED SILT FENCE REMOVED
9 3/1/2016 3/1/2016 Rex Amstutz In Compliance
10 3/15/2016 3/15/2016 Rex Amstutz Approved 1200-C LOG RETURNED TO CITY, SITE WAS STRAWED IAW WITH SUPV REQUIREMENTS