Development Permit Details
23 112082 00 PC
Permit- Number
- 23 112082 00 PC
- Type
- Public Construction - Subdivision - Water/Sewer/Street/Storm
- Status
- Permit Issued
- Details
- PC_FAIRVIEW ADD WEST PH 5
- Description
- FAIRVIEW ADDITION WEST PHASE 5 - 27-Lots The subject property totals approximately 32.98 acres in size, is zoned FMU (Fairview Mixed Use) within the Fairview Addition West Refinement Plan, and located at 2250 Strong Road SE (Marion County Assessors Map and Tax Lot Number(s): 083W1100200 & 00203; and 083W11BA08700).
Person Details
GREENSUNS INC
- Roles
- Contractor
- Address
-
PO BOX 71698
EUGENE OR 97475
WESTECH ENGINEERING INC
- Roles
- Engineer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
Property Details
Action Details
Application Intake
-
Make Ready To Issue (PW)
- Status:
- Approved
- Completed Date:
- 9/29/2023
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Assign Bin Number
- Status:
- Open
- Assigned Staff:
- PW Coordinator
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 9/29/2023
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 6/18/2024
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Fire Review
- Status:
- Approved As Noted
- Completed Date:
- 9/29/2023
- Assigned Staff:
- Fire Plan Review
- View Details
-
Agreement
- Status:
- Open
- Assigned Staff:
- Curtis Pellatz
Info
PW Inspections
-
As-Built Review
- Status:
- In Review
- Assigned Staff:
- PW Engineering
- View Details
-
Stormwater Treatment Inspection
- Status:
- Approved
- Completed Date:
- 10/14/2024
- Assigned Staff:
- PW Inspector
-
Sewer Tap Installation
- Status:
- Completed by City
- Completed Date:
- 10/14/2024
- Assigned Staff:
- PW Sewer
-
Storm Tap Installation
- Status:
- Completed by Applicant (No Refund Due)
- Completed Date:
- 10/14/2024
- Assigned Staff:
- PW Sewer
- View Details
-
10-month TV Inspection
- Status:
- Open
- Assigned Staff:
- PW Sewer
-
Sewer TV Inspection
- Status:
- Open
- Assigned Staff:
- PW Sewer
-
Storm TV Inspection
- Status:
- Approved
- Completed Date:
- 10/14/2024
- Assigned Staff:
- PW Sewer
- View Details
-
Chlorination <=12"
- Status:
- Completed by City
- Completed Date:
- 5/24/2024
- Assigned Staff:
- Greg Presser
- View Details
-
Erosion Control Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
Info
PW Water Inspections
-
Water Tap Installation
- Status:
- Open
- Assigned Staff:
- PW Water Group
-
Water Tap Installation
- Status:
- Open
- Assigned Staff:
- PW Water Group
Info