1 |
|
7/31/2025 |
Justin Padgett |
Inspected |
South manhole flowing into retention 8'' 3034 north then west, bushing down to 6''3034 at SW west of project approximately 150' |
2 |
|
8/1/2025 |
Justin Padgett |
Inspected |
South west catch basin to secondary catch. Basin 80' of 6'' 3034 Northwest to catch basin.
Ok to cover and continue. |
3 |
|
8/7/2025 |
Justin Padgett |
Inspected |
6'' 3034 Rain drain SW part of project for building.
8'' 3034 Rain drain s part of project, 8x6 y to 8'' C/O. 6'' 3034 heading east of why for rain drain and irrigation catch basins. |