Process Details

Description
Grout/Rebar Inspection
Folder Number
24 122021 00 BP
Folder Details
3010 KETTLE COURT SE
Permit Type
Building Permit - Commercial
Scheduled Date
8/25/2025
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 7/29/2025 Leif Nelson Inspected 1. MAINTAIN REQD CLEARANCE TO REBAR 2. INSTALL TRIM BARS AT RE-ENTRANT CORNERS ... BOTH PER PLAN ... THEN APPROVED SOG
2 8/11/2025 Leif Nelson Corrections 1. OBTAIN EOR'S APPROVAL FOR HIGH LIFT GROUTING AND PROVIDE CLEANOUT HOLES BOTH PER ACI STANDARD
3 8/12/2025 Chad Cooper Corrections INSP CANCELED BY CONTRACTOR.
4 8/13/2025 Leif Nelson Inspected CORRECTIONS OK ... APPROVED 1ST 12' LIFT
5 8/15/2025 Leif Nelson Inspected 1. ENSURE CLEAN CELLS FOR GROUT 2. MAINTAIN PROPER LAP SPLICE LENGTHS PER PLAN .... THEN APPROVED 2ND 12' LIFT AT ELEVATOR
6 8/15/2025 Leif Nelson Inspected COUNSEL
7 8/20/2025 Leif Nelson Inspected APPROVED NEXT LIFT OF CMU