Process Details

Description
Footing/Setback Inspection
Folder Number
24 122021 00 BP
Folder Details
3010 KETTLE COURT SE
Permit Type
Building Permit - Commercial
Scheduled Date
7/15/2025
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 6/6/2025 Chad Cooper Inspected PARTIAL- APPROVED ELEVATOR FOOTING W/ VERTS. PER DETAIL- 06/301 APPROVED AMENITY BLDG FOOTING E/ VERTS. PER DETAIL- 08/301
2 6/20/2025 Leif Nelson Corrections NO ACCESS AT 2:30 ...PLEASE RESCHEDULE W/ SUPERINTENDENTS CONTACT INFO
3 6/24/2025 Leif Nelson Inspected 1. ENSURE 3" CLEARANCE TO GRADE AND REMOVE ALL DEBRIS FROM FTGS ... THEN APPROVED ALL PERIMETER FTGS EXCEPT EAST END WHERE U-FER WILL BE LOCATED
4 7/2/2025 Chad Cooper Inspected PARTIAL- APPROVED REBAR FOR ELEVATOR PIT WALLS UP TO CMU LEVEL.
5 7/8/2025 PAC Portal Cancel Inspection Request Cancelled by PACPORTAL ()
6 7/10/2025 Leif Nelson Inspected 1. MAINTAIN REQUIRED CLEARANCES TO REBAR ... THEN APPROVED INDICATED INTERIOR PAD FTGS
7 7/15/2025 Leif Nelson Inspected APPROVED REMAING INTERIOR PAD FTGS WITH VERIFICATION OF RFI FROM EOR FOR CONDUITS THROUGH THEM .... NOTE: WET SETTING HD BOLTS AT THESE LOCATIONS