1 |
|
6/6/2025 |
Chad Cooper |
Inspected |
PARTIAL-
APPROVED ELEVATOR FOOTING W/ VERTS. PER DETAIL- 06/301
APPROVED AMENITY BLDG FOOTING E/ VERTS. PER DETAIL- 08/301 |
2 |
|
6/20/2025 |
Leif Nelson |
Corrections |
NO ACCESS AT 2:30 ...PLEASE RESCHEDULE W/ SUPERINTENDENTS CONTACT INFO |
3 |
|
6/24/2025 |
Leif Nelson |
Inspected |
1. ENSURE 3" CLEARANCE TO GRADE AND REMOVE ALL DEBRIS FROM FTGS ... THEN APPROVED ALL PERIMETER FTGS EXCEPT EAST END WHERE U-FER WILL BE LOCATED |
4 |
|
7/2/2025 |
Chad Cooper |
Inspected |
PARTIAL-
APPROVED REBAR FOR ELEVATOR PIT WALLS UP TO CMU LEVEL. |
5 |
|
7/8/2025 |
PAC Portal |
Cancel Inspection Request |
Cancelled by PACPORTAL () |
6 |
|
7/10/2025 |
Leif Nelson |
Inspected |
1. MAINTAIN REQUIRED CLEARANCES TO REBAR ... THEN APPROVED INDICATED INTERIOR PAD FTGS |
7 |
|
7/15/2025 |
Leif Nelson |
Inspected |
APPROVED REMAING INTERIOR PAD FTGS WITH VERIFICATION OF RFI FROM EOR FOR CONDUITS THROUGH THEM .... NOTE: WET SETTING HD BOLTS AT THESE LOCATIONS |