Process Details

Description
Grout/Rebar Inspection
Folder Number
24 122191 00 BP
Folder Details
1776 MILITIA WAY SE
Permit Type
Building Permit - Commercial
Scheduled Date
7/10/2025
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 4/30/2025 Leif Nelson Inspected APPROVED 5 SHEARWALL FTGS FOR POUR #1
2 5/6/2025 Leif Nelson Inspected APPROVED 7 SHEARWALL FTGS FOR POUR #2
3 5/7/2025 Leif Nelson Inspected APPROVED REMAINING SHEARWALL FTGS FOR POURS 3,4
4 5/21/2025 Leif Nelson Corrections 1. NEED TO VERIFY LEG LENGTH FOR REQUIRED HAIRPINS AT ENDS OF INDICATED WALLS AS WELL AS LENGTH OF 90 DEGREE CORNER RE-INFORCING ALSO INSTALL REQUIRED HAIRPINS AT HORIZONTAL DBA BARS . 2. MAINTAIN SEPERATION OF ALL BARS PER PLAN
5 5/23/2025 Leif Nelson Inspected CORRECTIONS OK FOR 7 INDICATED SHOTCRETE WALLS
6 7/2/2025 Matthew Smith Inspected
7 7/9/2025 Leif Nelson Inspected APPROVED 1ST AND 2ND AREAS FOR SOG POURBACKS
8 7/10/2025 Leif Nelson Inspected APPROVED REMAINING SLAB POURBACKS AT SHOTCRETE WALLS