1 |
|
1/7/2025 |
Ricardo Bojorquez |
Corrections |
ORSC 109.3 Provide electrical, plumbing, and mechanical rough approvals prior to framing inspection. Provide permits for each unit. Verify electrical box separation at 2 hour rated fire wall. Not a complete inspection. |
2 |
|
1/10/2025 |
Scott Morse |
Corrections |
R109.3 Please ensure completion and approval of MEP's before scheduling Framing inspection. |
3 |
|
1/13/2025 |
Ricardo Bojorquez |
Corrections |
ORSC 109.3 Previous corrections not made. Provide Mechanical and Plumbing rough inspections prior to framing inspection. |
4 |
|
1/14/2025 |
Ricardo Bojorquez |
Corrections |
ORSC R302.4.2.1 Per figure 302.4.2.1 Electrical outlets in 2 hour firewalls are required to be offset minimum 24". (laundry rooms O.K.)
ORSC 106.4 Maintain 1" airgap at truss assembly.
Recall for Fire separation inspections prior to insulation of fire walls.
ORSC 109.3 Complete exterior overhang framing prior to full framing approval |
5 |
|
1/16/2025 |
Ricardo Bojorquez |
Corrections |
Previous corrections not made |
6 |
|
1/21/2025 |
Ricardo Bojorquez |
Approved |
NOTE: Fire separation (rock wool) in 2 hour wall approved. Recall for insulation prior to sheetrock inspection. |