1 |
|
7/12/2024 |
Leif Nelson |
Inspected |
APPROVED FURR WALL AT EAST SIDE OF SPACE |
2 |
|
7/25/2024 |
Linda Evans |
Inspected |
|
3 |
|
7/26/2024 |
Leif Nelson |
Inspected |
APPROVED 1ST LAYER PLY SCREWS AND STRAPPING AT GAME MEZANNINE FLOOR ...ALSO EXTERIOR FURR WALL AT LASER TAG |
4 |
|
8/7/2024 |
Matthew Smith |
Inspected |
APPROVED ROOMS 202 AND 206 |
5 |
|
8/22/2024 |
Leif Nelson |
Inspected |
APPROVED INDICATED WALLS AND MEZANNINE |
6 |
|
8/30/2024 |
Matthew Smith |
Inspected |
APPROVED - TOWER |
7 |
|
10/4/2024 |
Leif Nelson |
Inspected |
APPROVED TOWER AND ADJACENT FRAMING |
8 |
|
10/16/2024 |
Leif Nelson |
Inspected |
APPROVED CONSESSIONS AREA |
9 |
|
11/26/2024 |
Leif Nelson |
Inspected |
APPROVED T-BAR AT INDICATED RMS |
10 |
|
1/29/2025 |
Leif Nelson |
Approved |
FOR FINAL |