1 |
|
8/1/2024 |
Sara Roth |
Corrections |
Did not install per plans. Devices not in code approved locations. FACP was moved and rooms changed; new devices were added. Did not perform the acceptance testing.
1. Submit as-builts for review of changes made.
2. Need approved revised plans on site for doc box.
3. Relocate devices in the office corridor. |
2 |
|
8/2/2024 |
Sara Roth |
Inspected |
Witnessed acceptance testing - Passed.
1. Cannot approve until as-builts are approved.
2. Need approved revised plans and ROC in doc box.
3. Need notification device in the north corridor relocated to withing 15' of the exit.
4. Candela in southwest classroom was adjusted at time of testing.
5. Record of Completion to The Compliance Engine |
3 |
|
8/5/2024 |
Sara Roth |
Approved |
Temp C/O until...
1. Approved revised plans and Record of Completion in the Document Box.
2. Record of Completion submitted to The Compliance Engine. |