Process Details

Description
PW Memo
Folder Number
24 105033 00 PLN
Folder Details
617 SAHALEE DRIVE SE
Permit Type
Planning - Type I
Scheduled Date
4/22/2024
Completed Date
5/10/2024
Assigned Staff
Jason Valyou

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 4/23/2024 Jason Valyou Routed To Routed to Survey for conformance review.
2 5/10/2024 Jason Valyou Complete At the time of final PLA submittal, the application shall provide the required field survey and Deed as per the statute and code requirements outlined in the Oregon Revised Statues (ORS) and the Salem Revised Code (SRC). If said documents are not in compliance with the requirements outlined in the ORS and the SRC, and as per SRC 205.055, the approval of the PLA by the City Surveyor may be delayed or held indefinitely based on the non-compliant violation.