Process Details
- Description
- Stormwater Treatment Inspection
- Folder Number
- 24 103963 00 PC
- Folder Details
- PC_WALN CREEK CROSSING
- Permit Type
- Public Construction - PW - Subdivision
- Scheduled Date
- 3/18/2024
- Completed Date
- 4/23/2025
- Assigned Staff
- PW Inspector
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 3/18/2024 | Daniel Parr | In Compliance | ||
2 | 4/23/2025 | Michael Martin | Approved | Pervious driveway installed per plan. Changes to filtration planter to be submitted with As-Builds. |