Process Details
- Description
- Planning Plan Review
- Folder Number
- 24 103963 00 PC
- Folder Details
- PC_WALN CREEK CROSSING
- Permit Type
- Public Construction - PW - Subdivision
- Scheduled Date
- 2/29/2024
- Completed Date
- 7/8/2024
- Assigned Staff
- Bryce Bishop
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 7/8/2024 | Curtis Pellatz | Approved | Good Afternoon Kim, The revised plans work for planning since the stormwater swales and utility lines are located outside of the critical root zones of the protected trees. Thanks, Bryce Bryce Bishop Planner III City of Salem | Community Planning and Development Department | Planning 555 Liberty St SE, Room 305 |