1 |
|
1/3/2024 |
Rex Amstutz |
Correction Notice |
started excavation with out placing bmps for erosion, covered at least one catch basin and dumped more spoils next to another catch basin, called left msg on Andrews phone stating to get erosion measures set prior to any more work to be done out side. |
2 |
|
1/8/2024 |
Rex Amstutz |
Correction Notice |
NO CHANGE, NO ACTIVITY, NO OGOING EXCAVATION |
3 |
|
1/11/2024 |
Rex Amstutz |
Correction Notice |
no change, im on site every day |
4 |
|
1/18/2024 |
Rex Amstutz |
Correction Notice |
NO CHANGE |
5 |
|
1/22/2024 |
Daniel Parr
|
Correction Notice |
No change |
6 |
|
1/29/2024 |
Daniel Parr
|
Correction Notice |
no change |
7 |
|
2/2/2024 |
Rex Amstutz |
In Compliance |
NO CHANGE CONTRACTOR NOT ON SITE |
8 |
|
2/16/2024 |
Daniel Parr
|
In Compliance |
no change |
9 |
|
3/1/2024 |
Kyle Anderson
|
Correction Notice |
EC measures not in place. implement immediately |
10 |
|
3/6/2024 |
Daniel Parr
|
Correction Notice |
No change since last inspection |
11 |
|
3/11/2024 |
Daniel Parr
|
Correction Notice |
no change |
12 |
|
3/14/2024 |
Daniel Parr
|
In Compliance |
|
13 |
|
3/28/2024 |
Daniel Parr
|
In Compliance |
|
14 |
|
4/11/2024 |
Daniel Parr
|
In Compliance |
|
15 |
|
4/25/2024 |
Daniel Parr
|
In Compliance |
|
16 |
|
5/9/2024 |
Daniel Parr
|
In Compliance |
|
17 |
|
5/23/2024 |
Daniel Parr
|
In Compliance |
|
18 |
|
6/7/2024 |
Michael Martin
|
In Compliance |
|
19 |
|
6/24/2024 |
Michael Martin
|
In Compliance |
|
20 |
|
7/9/2024 |
Michael Martin
|
In Compliance |
|
21 |
|
7/23/2024 |
Michael Martin
|
In Compliance |
|
22 |
|
2/4/2025 |
Darryl Rose
|
Approved |
|