Process Details

Description
Framing Inspection
Folder Number
23 110002 00 BP
Folder Details
375 MADRONA AVENUE S
Permit Type
Building Permit - Commercial
Scheduled Date
3/11/2024
Completed Date
3/28/2024
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 1/25/2024 Chad Cooper Inspected PARTIAL- APPROVED INTERIOR FRAMING AT NEW 2ND FLR OFFICES ON LINES B-F/ 4-6 APPROVED FRAMING AT AV AREA, BOTH FLRS ON LINES B-C/ 1-2
2 1/31/2024 Chad Cooper Inspected PARTIAL- APPROVED NEW FURRED WALL FRAMING AND FLOOR ANCHORS FOR BALCONY IN SANCTUARY.
3 2/12/2024 Chad Cooper Inspected PARTIAL- APPROVED BALCONY FRAMING- FLOOR JOIST, BEAMS AND COLUMNS. RECALL FOR PLATFORM FRAMING AND DRAFT STOP.
4 2/13/2024 PAC Portal Cancel Inspection Request Cancelled by PACPORTAL ([email protected])
5 2/15/2024 Chad Cooper Inspected PARTIAL- APPROVED METAL STUD FRAMING FOR MECH AND AV ROOMS. APPROVED PLATFORM FRAMING AND HORIZONTAL DRAFT STOPS FOR BALCONY. APPROVED FRAMING OF BALCONY GUARD WALL.
6 2/28/2024 Chad Cooper Inspected PARTIAL- APPROVED SUSPENDED HARDLID AT UNDERSIDE OF BALCONY.
7 3/11/2024 Chad Cooper Inspected PARTIAL- APPROVED CEILING GRID AT NEW 2ND FLR OFFICES AND HALL.
8 3/28/2024 Matthew Smith Approved