Process Details

Description
Framing Inspection
Folder Number
22 116266 00 BP
Folder Details
5775 COMMERCIAL STREET SE
Permit Type
Building Permit - Multi Family
Scheduled Date
6/20/2025
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 3/5/2024 Leif Nelson Inspected 1. COMPLETE ANCHOR BOLT INSTALLS AT MISSED SEPERATION WALLS AND WITHIN 12" OF ENDS OF PLATES AT EXTERIOR OPENINGS PER PLAN ... THEN APPROVED PT PLATE INSTALLS AND ANCHORBOLTS
2 4/24/2024 Leif Nelson Inspected COUNSEL ONLY
3 8/19/2024 Matthew Smith Inspected IN PROGRESS
4 8/22/2024 Leif Nelson Inspected APPROVED CORRIDOR LIDS FOR ROCK
5 9/11/2024 Leif Nelson Inspected APPROVED BEHIND TUB/SHOWERS 1ST AND 2ND FLOOR
6 10/31/2024 Chad Cooper Inspected PARTIAL- APPROVED FRAMING BEHIND TUBS/ SHOWERS ON 3RD AND 4TH FLRS. **INSTALL NAIL PLATES FOR PLUMBING PENETRATIONS AT TOP AND BOTTOM PLATES AND STUDS PRIOR TO SHEETROCK.
7 12/6/2024 Leif Nelson Inspected APPROVED 2ND FLOOR FRAMING ... NOTE: DO NOT INSULATE LIDS UNTIL ROUGH MECHANICAL IS APPROVED
8 12/13/2024 Matthew Smith Inspected APPROVED BEHIND TUB/SHOWERS 3RD AND 4TH FLOORS
9 12/16/2024 Leif Nelson Inspected APPROVED 3RD FLOOR UNITS
10 12/26/2024 Leif Nelson Inspected APPROVED 4TH FLOOR
11 1/31/2025 Leif Nelson Inspected APPROVED 1ST FLOOR UNITS ... LEASE AND OFFICE SPACE TO COME
12 4/23/2025 Leif Nelson Inspected 1. FIRECAULK MISSED PENETRATIONS AT RATED WALLS 2. PATCH AND REPLACE SHEETROCK AS DISCUSSED 3. FIREBLOCK TOP PLATE OF FURRED WALL ALL PER PLAN ... THEN APPROVED SALES OFFICES EXCEPT BATHROOM