1 |
|
11/9/2023 |
Matthew Smith |
Inspected |
APPROVED EXTERIOR FOOTINGS - FORMS REBAR - MIDDLE WEST SECTION FOR ACCESS TO BE INSTALLED AT LATER DATE |
2 |
|
12/13/2023 |
Leif Nelson |
Inspected |
1. SUPPLY WRITTEN OK FROM EOR FOR SHORT EMBEDMENT OF SSTB24 HD'S ...VERBAL REVEIVED ... APPROVED EXTERIOR FDTN WALLS EXCEPT ENTRY POINT LEFT OUT |
3 |
|
12/20/2023 |
Leif Nelson |
Inspected |
1. APPROVED ELEEVATOR PIT SOG ... ALSO INDICATED INTERIOR PAD FTGS |
4 |
|
1/3/2024 |
Leif Nelson |
Inspected |
COMPLETE VERT INSTALLS PER PLLAN AT NORTH STAIR ... THEN APPROVED 2 STAIR SOG'S ALSO ELEVATOR PIT WALLS |
5 |
|
2/16/2024 |
Chad Cooper |
Inspected |
PARTIAL-
1. APPROVED SLAB REBAR AT LINES- 1-2/ B-F. LINES- 2-4.3/ A-D
2. COMPLETE INTERIOR FOOTING REBAR REPLACEMENT TO #5 BARS AND PROVIDE SPECIAL INSP REPORT FOR APPROVAL. |
6 |
|
9/9/2024 |
PAC Portal |
Cancel Inspection Request |
Cancelled by PACPORTAL ([email protected]) |
7 |
|
9/11/2024 |
Leif Nelson |
Approved |
APPROVED SOG AT ELECTRIC / RISER RM |