Folder Number
22 121638 00 CO
Folder Details
CO-MAHONIA CROSSING PH 2_5120 SALAL STREET SE
Permit Type
Commercial Permit - DS - Multi Family
Scheduled Date
12/16/2024
Completed Date
1/17/2025
Assigned Staff
PW Inspector

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 6/18/2024 Michael Martin Inspected Phase 2 of this project is still being heavily worked on. Not ready for final PW inspection.
2 8/29/2024 Kyle Anderson Inspected Not Ready for Final. WQ Pond not finished and EC measures not removed from site.
3 10/24/2024 Kyle Anderson Inspected Not Ready
4 12/16/2024 Kyle Anderson Inspected Punch List Started
5 1/17/2025 Curtis Pellatz Approved Per Kyle Anderson, Okay to Approve.