1 |
|
9/15/2023 |
Michael Conkey
|
Corrections |
Grading not started yet, no fencing up. |
2 |
|
9/22/2023 |
Michael Conkey
|
Corrections |
Called WESTECH ENGINEERING INC who advised that Willamette Valley Excavating is doing the work and they would know when they will have tree protections in placed, called them at 503-507-9460 and Left VM to call me back with start date. |
3 |
|
10/2/2023 |
Michael Conkey
|
Corrections |
Spoke with Austin, the project manager, at Willamette Valley Excavating 503-507-9460 and stated estimated start date is 2 weeks out. |
4 |
|
10/16/2023 |
Michael Conkey
|
Corrections |
Spoke with Austin - Pending NW Natural Gas Line work before grading - should have tree protection in about 2-3 more weeks. |
5 |
|
10/25/2023 |
Michael Conkey
|
Approved |
Spoke with Seth and Rodney on site, explained code recently changed from dripline to 1' per inch DBH, we measured out the distance and now match's the plans. Explained the CRZ to him. Had questions as there is a cement pad from old building that is partially in CRZ, and slight dirt fill, in that area. Spoke with Planner Bryce B to see if any more info was needed, the removal of the the old building is taken into account on the CRZ and the fill does no show a change in contour so no additional arborist review needed. |