Comment Number Scheduled Date Comment Date Staff Result Comment
1 11/9/2023 Matthew Smith Inspected LOWER DRAG CONTECTORS
2 11/30/2023 Leif Nelson Inspected COUNSEL ONLY
3 12/8/2023 Leif Nelson Inspected APPROVED ALL FLOORS AND ROOF METAL DECK INSTALLS
4 1/2/2024 Leif Nelson Inspected APPROVED PARAPET WALLS
5 1/3/2024 Leif Nelson Inspected 1. ADD ADDITIONAL FASTNERS TO CURBS PER ENGINEERING ... THEN APPROVED RTU CURBS TO STRUCTURE CONNECTIONS
6 4/9/2024 Leif Nelson Inspected APPROVED WALL FRAMING AT STAIRS AND ELEVATOR
7 4/16/2024 Leif Nelson Inspected APPROVED 1ST FLOOR WALLS AND HARD LIDS
8 4/19/2024 Leif Nelson Inspected 1. SEAL ALL PENETRATIONS FLOOR TO FLOOR FOR SMOKE PER OSSC 717 ... THEN APPROVED WALLS AND HARD LIDS AT 2ND AND 3RD FLOORS EXCEPT INSIDE OF STAIRS
9 5/6/2024 Leif Nelson Inspected APPROVED SUSPENDED HARD LID OVER SOUTH STAIRS ...ALSO APPROVED FRAMING FOR BEAM WRAPPING
10 5/23/2024 Leif Nelson Inspected APPROVED NORTH STAIRWELL
11 6/14/2024 Leif Nelson Inspected APPROVED 1ST FLOOR CORRIDORS T-BAR ALSO CLASS RM T-BAR FOR BORDER COVER
12 6/18/2024 Leif Nelson Inspected APPROVED REMAINING T-BAR ALL FLOORS EXCEPT INDICATED AREA 1ST FLOOR
13 7/12/2024 Leif Nelson Approved APPROVED T-BAR AT ELEVATOR LOBBY