Process Details

Description
Sheetrock Nailing Inspection
Folder Number
22 117292 00 BP
Folder Details
155 COTTAGE ST NE
Permit Type
Building Permit - Commercial Phased
Scheduled Date
8/15/2024
Completed Date
11/18/2024
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 9/18/2023 Roberto Rios Corrections Wrong inspection type requested/ Actual inspection for roof nailing
2 1/4/2024 Roberto Rios Inspected APPROVED SECOND FLOOR CEILING RATED SOFFIT AREA
3 3/4/2024 Roberto Rios Inspected SECOND FLOOR APPROVED EXCEPT NE CORNER
4 3/15/2024 Roberto Rios Inspected Second floor sheetrock approved to mud
5 3/22/2024 Roberto Rios Inspected INSPECTED HARD LID AT 2ND FLOOR CEILING HALLWAY SECTION BY CENTER STAIRS 3RD FLOOR WALL COVER INSPECTED
6 5/2/2024 Roberto Rios Inspected 5TH FLOOR/ CLEAR STORY-HARD LID
7 5/9/2024 Roberto Rios Inspected 4TH FLOOR SHEETROCK / PERIMETER TO FOLLOW
8 5/15/2024 Roberto Rios Inspected 5TH FLOOR SHEETROC APPROVED / ENSURE COMPLETION OF REQUIRED FIRE CAULKING AS DISCUSSED
9 5/23/2024 Roberto Rios Inspected INTERIOR SHEETROCK 4TH FLOOR NW CORNER IDF RM AND ELECTRICAL RM FIRST FLOOR EXTERIOR WALL INSULATION BASEMENT AREA
10 6/10/2024 Roberto Rios Inspected FIRST FLOOR PARTIAL
11 6/17/2024 Roberto Rios Inspected RATED SHAFT WALL NORTH AND SOUTH L1
12 6/21/2024 Roberto Rios Inspected STAIR # 3 SHEETROCK FASTENING AND 2ND FLOOR T-GRID PARTIAL
13 6/24/2024 Roberto Rios Inspected MECHANICAL ROOM SHAFT WALL EAS AND WEST SECTIONS/ FIRST FLOOR SHEETROCK
14 7/8/2024 Roberto Rios Inspected STAIR 1 / FLOORS1-4
15 7/31/2024 Roberto Rios Inspected STAIR # 2 / 4TH TO 5TH FLOORS
16 8/15/2024 Roberto Rios Inspected stair 2 completed
17 11/18/2024 Roberto Rios Approved