Process Details

Description
Insulation Inspection
Folder Number
22 117292 00 BP
Folder Details
155 COTTAGE ST NE
Permit Type
Building Permit - Commercial Phased
Scheduled Date
4/26/2024
Completed Date
11/18/2024
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 2/29/2024 Roberto Rios Inspected SECOND FLOOR INTERIOR INSULATION INCLUDES MECHANICAL ROOM
2 3/13/2024 Matthew Smith Inspected REMANING AREAS 2ND FLOOR AND BASEMENT
3 3/26/2024 Roberto Rios Corrections CANCELLED BY CO/ CALLED LEFT MESSAGE AT 503-459-6713
4 3/28/2024 Roberto Rios Inspected 2nd and third floors perimeter insilation nd fireproofing floor to floor
5 4/12/2024 Roberto Rios Approved Thermal and Sound insulation second and third floors
6 4/25/2024 Katie Alaga Inspected
7 4/26/2024 Roberto Rios Inspected 5th floor clear story
8 11/18/2024 Roberto Rios Approved