Process Details

Description
DS Plan Review
Folder Number
23 103934 00 PC
Folder Details
PC_COBURN GV ESTATES Phase 1
Permit Type
Public Construction - PW - Subdivision
Scheduled Date
4/29/2025
Assigned Staff
Curtis Pellatz

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 3/29/2023 Curtis Pellatz In Review
2 4/21/2023 Curtis Pellatz Info Requested PRC1 Plan Review Comments routed to MTE
3 6/26/2023 Curtis Pellatz Info Received Recv'd Revised Plans and supporting material. Routed for Review
4 7/21/2023 Curtis Pellatz Info Requested PRC2 Plan Review Comments routed to MTE via ShareFile Jeremy, Please follow the link to the Plan Review Comments (PRC2) for the above-mentioned project. https://cityofsalem.sharefile.com/home/shared/fod1dee6-4d97-46ab-a172-71f8a0281f87 Please be sure to submit the deign plans for the required off-site improvements for the development as required by the Land Use Decision. Thanks, Curt Pellatz Senior Program Manager
5 10/24/2023 Curtis Pellatz Info Requested To Date, no new information received on Public Construction Plans
6 2/16/2024 Curtis Pellatz Info Received Design Exception request received. (Ped Crossing eliminated). Routed for Review
7 2/21/2024 Curtis Pellatz Info Received Received Complete PC Plan Set. Routed for Review.
8 3/11/2024 Curtis Pellatz Info Requested PRC Plan Review Comments (PRC3) provided to MTE via ShareFile.
9 4/26/2024 Curtis Pellatz Info Received Recv'd Revised Plans and Stormwater Report. Routed for review.
10 5/15/2024 Curtis Pellatz Info Requested PRC4 Plan Review Comments provided to MTE via ShareFile.
11 6/21/2024 Curtis Pellatz Info Received Recv'd Revised Plans and Storm Report. Routed for Review
12 7/15/2024 Curtis Pellatz Info Requested PRC5 Plan Review Comments provided to MTE via ShareFile
13 8/16/2024 Robin Dalke Info Received Revised plans, drainage report and response comments rec'd. Routed in BB.
14 8/29/2024 Curtis Pellatz Info Requested Hi Jeremy, Please follow the link to the Plan Review Comments (PRC6) for COBURN GV. Ive also included the Approved Storm Report in this folder. https://cityofsalem.sharefile.com/home/shared/foe19324-40ea-44b4-96b3-c6dc04881e99 Any update on the Reed/Battle Creek Road intersection improvement drawings? Thanks, Curt Pellatz | Work: 503-584-4644 City of Salem | Community Planning and Development | Development Services
15 9/12/2024 Curtis Pellatz Info Received Recv'd Revised Plans. Routed for review.
16 10/8/2024 Curtis Pellatz Info Requested PRC7 provided to MultiTech Engineering.
17 3/18/2025 Curtis Pellatz Info Requested On-Site Plans can be Approved. Still need Engineer's Estimate including Approved Plans and Estimate for off-site improvements (Reed/Battle Creek, Condition 23).