1 |
|
6/15/2023 |
Justin Guinan |
Inspected |
Riser manifolds are too short for the footing.
Waiting for revisions and letter from engineer explaining corrections. |
2 |
|
6/21/2023 |
Justin Guinan |
Inspected |
Inspected thrust blocks on 1-8 |
3 |
|
8/1/2023 |
Justin Guinan |
Inspected |
Inspected piping and hydrant near guard shack |
4 |
|
8/16/2023 |
Justin Guinan |
Inspected |
Inspected additional thrust blocks x3 |
5 |
|
8/25/2023 |
Justin Guinan |
Inspected |
Will reschedule. |
6 |
|
9/5/2023 |
Justin Guinan |
Inspected |
Not doing water line today, will call in a few days. |
7 |
|
9/12/2023 |
Justin Guinan |
Inspected |
Plans marked. |
8 |
|
9/13/2023 |
Justin Guinan |
Inspected |
Plans marked, ok for cover. |
9 |
|
9/15/2023 |
Justin Guinan |
Inspected |
Ok for cover. |
10 |
|
9/20/2023 |
Robert Johnson |
Inspected |
No contact info. Went on site.
Terry was not there at this time. Did not see approved plans as they were with him supposedly.
Work crews taking pictures of underground as they bury it.
Cover at own risk. |
11 |
|
9/25/2023 |
Justin Guinan |
Inspected |
ok for cover |
12 |
|
9/28/2023 |
Justin Guinan |
Inspected |
Ok for cover. |
13 |
|
10/27/2023 |
Justin Guinan |
Inspected |
Cover ok, marked in pink. |
14 |
|
11/16/2023 |
Janet Campbell |
Inspected |
Cover ok, marked with pen on wall plans inside office for Elijah. |
15 |
|
2/29/2024 |
Justin Guinan |
Inspected |
Inspected UGFL by the FMF. Cover ok. |
16 |
|
3/4/2024 |
PAC Portal |
Cancel Inspection Request |
Cancelled by PACPORTAL ([email protected]) |
17 |
|
3/8/2024 |
Justin Guinan |
Inspected |
Hydro passed. Spilt into two sections, north and south. |