1 |
|
7/11/2023 |
Clint Barber |
Inspected |
MH A-1 to MH A-2
test at later date. |
2 |
|
7/18/2023 |
Matthew Smith |
Inspected |
MH A5 - MH A6 |
3 |
|
7/25/2023 |
Clint Barber |
Inspected |
Sewer line A from MH-A6 to MH-A6, sewer line C from MH-A6 to guardhouse. |
4 |
|
8/16/2023 |
Matthew Smith |
Inspected |
APPROVED Sanitary Sewer Line B A1 to B1 |
5 |
|
8/23/2023 |
Clint Barber |
Inspected |
Approved Sanitary sewer line B . |
6 |
|
11/6/2023 |
Matthew Smith |
Inspected |
APPROVED FROM MH A-7 TO A-10 |
7 |
|
1/19/2024 |
Matthew Smith |
Inspected |
SS A1 -B1 - COMPLETE AIR AND VIDEO TO COME |
8 |
|
6/21/2024 |
Matthew Smith |
Inspected |
APPROVED -FMF Sanitary Sewer Connection to Manhole A5 |