Process Details
- Description
- Final Structural Inspection
- Folder Number
- 22 109717 00 BP
- Folder Details
- 5120 SALAL STREET SE (BLDG E)
- Permit Type
- Building Permit - Commercial
- Scheduled Date
- 10/14/2024
- Completed Date
- 10/14/2024
- Assigned Staff
- Leif Nelson
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 4/22/2024 | Leif Nelson | Inspected | RECEIVED SPECIAL INSPECTION FINAL LETTER | |
2 | 5/24/2024 | Leif Nelson | Corrections | NOT READY PER OSSC 109 | |
3 | 6/3/2024 | Leif Nelson | Inspected | 1. COMPLETE SIGNAGE AT ADA PARKING 2. COMPLETE PERMANENT RAILS AT STAIRS, RAMP AND AT ELEVATED WALKWAY AT DECK AREA( TEMPORARY RAILS IN PLACE ... OK FOR TCO | |
4 | 10/14/2024 | Leif Nelson | Approved | 1. ENSURE ALL OTHER DISCIPLINES APPROVALS |