1 |
|
9/21/2022 |
Curtis Pellatz
|
Revisions Requested |
Good Morning,
Public Works has received the proposed Civil Site Work plans, Storm Report, and Landscaping plans for the proposed Industrial Development at 4405 Turner Road SE, submitted to the Building & Safety on Permit No. 22-118667-BP.
Public Works will be reviewing and issuing permit under the following Permit Nos.
Civil Site Work: 22-119230-CO
Public Construction: 22-119231-PC (Turner Road and Fire Service Connection)
We have calculated the Public Works Plan Review Fee based on the development site area of 10.2 Acres. Prior to routing the plans and reports for full City Staff review, we will need payment of the following Plan Review Fees.
City Permit No: 22-119230-CO
Plan Review Fees Due: $42,947.00
This fee is available for payment through the Citys Pac Portal Web Site. https://egov.cityofsalem.net/PACPortal
I understand that an Appeal of the Land Use Decision has been filed, related to the required Turner Road Street Improvements. Please note, that a full and complete review of the Turner Road Street Improvement plans may not provided until the Appeal is resolved.
Please feel free to contact me if you have any questions.
Thank you,
Curt Pellatz
Senior Program Manager |
2 |
|
9/26/2022 |
Curtis Pellatz
|
Revisions Requested |
Good Morning,
I understand that there was meeting last week to discuss the required Turner Road improvements related to the 4405 Turner Road Industrial development. I just wanted to check to see how you want to proceed with the review of this project.
Plan Review fees have been paid, and we have received the Civil Site Work (On-Site) plans. We can route these plans, without the Turner Road Improvement plans, but they will likely not receive a full review. Or,
We can wait until the Public Construction plans for the Turner Road Improvements are submitted and route the full package for full Staff review.
Please let me know how you would prefer to proceed with the review of this project.
Thank you,
-Curt | 503-588-6211 ext. 7442 |
3 |
|
9/27/2022 |
Curtis Pellatz
|
Revisions Received |
Per Applicant. Public Construction plans for Turner Road Improvements will be submitted at a later date. Requested Civil Site Work plans to be reviewed. |
4 |
|
10/12/2022 |
Curtis Pellatz
|
Revisions Requested |
Craig,
Public Works has completed our first review on the on-site improvements for the 4405 Turner Road Industrial Development in Salem. Please follow this link for access to those files.
https://cityofsalem.sharefile.com/home/shared/fo1b8aae-d927-4f9f-99fb-a6051578bcb6
When resubmitting plans, we will need a written response to each Plan Review Comment provided. Please feel free to contact me if you have any questions.
Please note, no comments are being provided on the Turner Road improvements, as we are expecting full design drawings at a later date.
Again, please feel free to contact me if you have any questions.
Thank you,
Curt Pellatz |
5 |
|
11/7/2022 |
Curtis Pellatz
|
Info Received |
Revisions Recv'd and routed for review |
6 |
|
11/23/2022 |
Curtis Pellatz
|
Info Requested |
PRC2 provided to Project Engineer through ShareFile |
7 |
|
1/30/2023 |
Curtis Pellatz
|
Info Received |
Recv'd Revised Civil Site Work and Public Construction plans. Routed for Review. |
8 |
|
2/17/2023 |
Curtis Pellatz
|
Info Requested |
PRC3 to Project Engineer:
Christopher,
Please follow this link to the Plan Review Comments (PRC3) for the Turner Road Industrial located 4405 Turner Road, Salem. Please download the files (Civil Site Work, Public Construction, Landscaping, Storm Report, and Warranty Deed Template) and review the comments. As always, if you would like to meet with Staff to discuss the comments, please feel free to request a meeting.
https://cityofsalem.sharefile.com/home/shared/foc7abf3-b23e-4e47-bcf6-13c0b111c5c3
Feel free to contact me anytime if you have any questions.
Thanks,
-Curt | 503-588-6211 ext. 7442 |
9 |
|
3/23/2023 |
Curtis Pellatz
|
Info Received |
Recv'd revised Civil Plans, PC Plans, Landscaping, and Stormwater Report. Routed for Review. |
10 |
|
4/10/2023 |
Curtis Pellatz
|
Info Requested |
PRC4 Plan Review Comments routed to Design Engineer through Share File.
Chris,
Please follow the link to the Plan Review Comments (PRC4) for the TURNER ROAD IND project in Salem.
https://cityofsalem.sharefile.com/home/shared/fo5ddedf-e270-46ad-8836-6ef368456405
I think that it would be good to schedule a meeting with you and our Engineering Department to discuss the comments. Our main reviewer, Don Whitehurst, has requested a meeting with you and your Geotech Engineer to go over the Turner Road design.
Please download and review the comments, and let me know when youre ready to schedule a meeting and I can provide some dates and times.
Thanks,
-Curt | 503-588-6211 ext. 7442 |
11 |
|
5/3/2023 |
Curtis Pellatz
|
Info Received |
Recv'd revised Civil Site Work and Public Construction Plans. Routed for Review |
12 |
|
5/18/2023 |
Curtis Pellatz
|
Info Requested |
PRC5 Plan Review Comments routed to AAI Engineering. Met with the Project Engineer to discuss the comments. |
13 |
|
5/23/2023 |
Curtis Pellatz
|
Info Received |
Recv'd revised Civil Site Work and PC Plans, Storm Report, and Design Exception Request. Routed for Review. |
14 |
|
5/26/2023 |
Curtis Pellatz
|
Approved |
|