1 |
|
7/18/2022 |
Matthew O'Donnell
|
Info Requested |
Sent plan review letter to applicant. Matt O. 7/18/2022 |
2 |
|
8/18/2022 |
Carrie Harper |
Info Received |
Secondary |
3 |
|
8/19/2022 |
Matthew O'Donnell
|
Info Requested |
Spoke to applicant. Waiting for comcheck and engineered calculations for covered area.
Matt O. 8/19/2022 |
4 |
|
8/26/2022 |
Carrie Harper |
Info Received |
Secondary |
5 |
|
8/26/2022 |
Matthew O'Donnell
|
Info Requested |
Waiting for engineering packet to be provided. Comcheck provided.
Matt O. 8/26/2022 |
6 |
|
9/2/2022 |
Mareva Massey
|
Info Received |
Secondary |
7 |
|
9/6/2022 |
Matthew O'Donnell
|
Info Requested |
Sent revised plan review letter and spoke to architect. Needing special inspection to be provided (attached to plan review letter email sent).
Matt O. 9/6/2022 |
8 |
|
10/3/2022 |
Carrie Harper |
Info Received |
Secondary |
9 |
|
10/7/2022 |
Matthew O'Donnell
|
Approved |
|
10 |
|
10/7/2022 |
Matthew O'Donnell
|
Approved |
|