1 |
|
8/15/2022 |
Leif Nelson |
Inspected |
COUNSEL ONLY |
2 |
|
9/26/2022 |
Leif Nelson |
Corrections |
COMPLETE COLD ROLL INSTALLS INCLUDING LAP DETAIL AND ATTACH TO STUDS AND ORIENT IT CORRECTLY ALL PER PLAN |
3 |
|
12/13/2022 |
Leif Nelson |
Inspected |
1. COMPLETE WALL HEAD FURRING TO ALLOW FOR DEFLECTION AT EAST/WEST WALL EAST END OF BLDG ... THEN APPROVED FRAMING AT NORTH SOUTH MAIN WALL AND CALL FOR INSPECTION WHEN OTHER WALL HEAD IS COMPLETE |
4 |
|
12/20/2022 |
Leif Nelson |
Inspected |
WALL HEAD FURRING ON EAST/WEST 2 HR WALL |
5 |
|
1/11/2023 |
Leif Nelson |
Inspected |
APPROVED WALLS AT NE CORNER |
6 |
|
3/2/2023 |
Leif Nelson |
Inspected |
APPROVED WALLS AT ELEC. EQUIP. RM |
7 |
|
3/17/2023 |
Leif Nelson |
Inspected |
APPROVED CURB LEVELER TO STRUCTURE CONNECTIONS 4 TOTAL ...STILL NED TO VERIFY CURB TO CURB LEVELER CONNECTIONS |
8 |
|
4/27/2023 |
Leif Nelson |
Inspected |
APPROVED EAST DOG HOUSE |
9 |
|
5/17/2023 |
Leif Nelson |
Inspected |
1. PROVIDE CLARIFICATION FROM EOR FOR X-BRACING AT NORTH WINGS OF ENTRY PER PLAN ... OK TO COVER EXTERIORS OF ENTRY |
10 |
|
5/24/2023 |
Matthew Smith |
Inspected |
APPROVED EXTERIOR SHEATHING - ENTRANCE TOWERS |
11 |
|
6/7/2023 |
Leif Nelson |
Inspected |
APPROVED REMAINING FRONT ENTRY FACADE FRAMING |