Process Details

Description
DS Plan Review
Folder Number
20 118530 03 PC
Folder Details
PC-EAST PARK PH 3
Permit Type
Public Construction - PW - zzArchive - SUB - Major Facilities
Scheduled Date
8/3/2022
Completed Date
8/5/2022
Assigned Staff
Curtis Pellatz

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 6/17/2022 Curtis Pellatz In Review Routed for Review
2 7/4/2022 Curtis Pellatz Revisions Requested Jeremy, Please follow the link to the Plan Review Comments (PRC1) related to the proposed culvert crossings at the EST PARK PH 3 project. https://cityofsalem.sharefile.com/home/shared/foa413ef-aaa7-4211-9c38-a9facfd7a58e Thank you, Curt Pellatz Senior Program Manager
3 7/13/2022 Curtis Pellatz Revisions Received Recv'd revised Plans and Headwall Calculations.
4 7/19/2022 Curtis Pellatz Info Received Recv'd Headwall Detail Sheet (314) and Headwall Calculations
5 8/1/2022 Curtis Pellatz Revisions Requested Hi Jeremy, I believe that this is the last remaining comment that we have for the EAST PARK Storm Crossings. I believe that the Culverts, Headwall Details, Storm Crossings (Greencrest & Lost Lake), and Headwall Structural Analysis are all ready to be Approved. Please see the attached PRC2 Plan Review Comments for the Storm Crossing @ Redmond. Regarding the ODFW Applications, I think that Lost Lake and Redmond are Private Streets, and the Greencrest crossing hasnt been accepted as public right-of-way yet. Im not sure that the City would the Applicant on any of these at this time. Let me know your thoughts. Thanks, Curt Pellatz Senior Program Manager City of Salem | Public Works Department
6 8/2/2022 Curtis Pellatz Revisions Received Recv'd Revised REDMOND Storm Crossing plan (Sheet 317). Routed to Don for Review
7 8/5/2022 Curtis Pellatz Approved