1 |
|
6/8/2022 |
Timothy Gorton |
Corrections |
1. Vault to building has BlazeMaster= okay.
2. City water valve to vault has Pex material= not okay.
3. Entire length of fire line must be BlaseMaster or Ductile Iron. |
2 |
|
6/16/2022 |
Sara Roth |
Corrections |
Approved plans not on site. Scott asked for a later inspection to finish, but said he would not available to be on site for the inspection. I denied the request due to no approved plans.
1. Vault to building has BlazeMaster= okay.
2. City water valve to vault has Pex material= not okay.
3. Entire length of fire line must be BlaseMaster or Ductile Iron. |
3 |
|
6/17/2022 |
Sean Mansfield |
Inspected |
witness blazemaster from valve to vault. |
4 |
|
8/5/2022 |
Sean Mansfield |
Inspected |
witness underground flush-okay |
5 |
|
9/6/2022 |
Sara Roth |
Inspected |
Witnessed flush of FDC - Passed clean. Need to have approved plans on site at time of next inspection. |
6 |
|
9/7/2022 |
Sean Mansfield |
Corrections |
HYDRO TEST FAILED |
7 |
|
2/3/2023 |
Jordan Wakem |
Approved |
TCO until CMTC is submitted to DFM. Left my business card. |