1 |
|
5/4/2022 |
Curtis Pellatz
|
Revisions Requested |
Waiting on Land Use Decision and Apartment Civil Site Work plans to be submitted. |
2 |
|
8/5/2022 |
Curtis Pellatz
|
Revisions Requested |
To Date, no new information recv'd |
3 |
|
2/13/2023 |
Curtis Pellatz
|
Info Requested |
To Date, Waiting on full Civil Site Work package to be submitted from Applicant. |
4 |
|
2/14/2023 |
Curtis Pellatz
|
Info Received |
Recv'd Storm Report for Apartment Complex. Routed entire review package for Staff Review. |
5 |
|
3/22/2023 |
Curtis Pellatz
|
Info Requested |
Please follow the link to the Plan Review Comments (PRC3) for the above-mentioned project.
https://cityofsalem.sharefile.com/home/shared/foa30b19-ee08-4e00-be29-f1cabd4a20ee
Thanks,
Curt Pellatz
Senior Program Manager |
6 |
|
8/3/2023 |
ProjectDox Access |
Info Requested |
|
7 |
|
2/24/2025 |
Curtis Pellatz
|
Info Received |
Recv'd Revised Civil Site Work & Pubic Construction plans for review. |
8 |
|
3/13/2025 |
Curtis Pellatz
|
Info Requested |
PRC6 provided to MTE:
Good Morning,
Please follow this link to Plan Review Comments (PRC6) for the COBURN GV Apartments project.
https://cityofsalem.sharefile.com/home/shared/foda386a-9e19-47a3-89d0-0f01b7220e33
Thank you,
Curt Pellatz
Development Program Manager II |
9 |
|
3/13/2025 |
Curtis Pellatz
|
Info Requested |
PRC6 Plan Review Comments provided to MTE |
10 |
|
4/4/2025 |
Curtis Pellatz
|
Info Received |
Revised Plans Received. Routed for Review |
11 |
|
4/21/2025 |
Curtis Pellatz
|
Info Requested |
PRC7:
Good Morning Jeremy,
Please follow this link to the Plan Review Comments (PRC7) for the Coburn GV Apartments project.
https://cityofsalem.sharefile.com/home/shared/fo944788-4e58-4986-b38f-77e32bbc17b3
Thank you,
Curt Pellatz | Work: 503-584-4644 |
12 |
|
4/21/2025 |
Curtis Pellatz
|
Info Requested |
PRC7 provided to MultiTech Engineering via separate email. |