1 |
|
5/3/2022 |
Curtis Pellatz
|
|
Terry Hockett and Aaron Edelman Comments emailed to MultiTech Engineering. |
2 |
|
5/3/2022 |
Curtis Pellatz
|
|
Routed 04-13-22 Signal Plans to Terry H. |
3 |
|
5/4/2022 |
Curtis Pellatz
|
|
Curtis/Jeremy,
The traffic plans dated 4/8/2022 do not address the following comment we received today (5/3/22) from Multitech (see red text below). We are in the process of updating the service cabinet detail (TS-6) and will update foundation information on TS-4 once we receive the revised foundation depths from the structural engineer.
Terry,
A couple questions for you:
"The pole designations and mast arm lengths for Pole Nos. 4, 7, and 10 do not match between the construction drawings and the Structural Analysis for Traffic Signal Pole Foundation Design (dated 01/12/22). Given the Construction Note (diamond #3), I am unsure what should be the correct document. This difference will impact the overall foundation depths currently shown on TS-3.
"Also, did you supply Kittelson with the updated hinged service cabinet drawing? TS-5 appears to show the older model that PGE will no longer energize.
Thanks.
-Aaron A. Edelman | 503-588-6211 ext. 7363
Anthony S. Yi, P.E. | Kittelson & Associates, Inc.
d: (503) 535-7415 | o: (503) 228-5230 | c: (503) 421-2502 |
4 |
|
5/9/2022 |
Curtis Pellatz
|
|
Revised Signal Plans and Structural Calcs received and emailed to Terry H and Aaron E. |
5 |
|
5/17/2022 |
Curtis Pellatz
|
|
Hi Jeremy,
Please follow the link to Terry Hockett's and Aaron Edelman's comments related to the Auburn/Cordon Traffic Signal.
Thanks, Curt |
6 |
|
6/30/2022 |
Curtis Pellatz
|
|
Recv'd revised Signal, Interconnect, Cabinet Plans. Routed for review |
7 |
|
7/14/2022 |
Curtis Pellatz
|
Redlines - Revisions Requested |
Signal Plan Review Comments (PRC12) (Terry Hockett's Comments) routed to MultiTech Engineering via ShareFile. |
8 |
|
1/11/2023 |
Curtis Pellatz
|
Complete - No Redlines |
To Date, No New information Received. New Land Use Decision (CPC-ZC-PUD-SUB-ADJ19-08MOD2) moves the Auburn/Cordon Signal requirement to Phase 4.
Moved Review process to Phase 5 22-104143-PC. |