Process Details

Description
DS Plan Review
Folder Number
21 122245 00 PC
Folder Details
PC - SCANNELL SUBDIVISION
Permit Type
Public Construction - PW - zzArchive - SUB - Major Facilities
Scheduled Date
9/29/2022
Completed Date
12/4/2022
Assigned Staff
Curtis Pellatz

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 2/14/2022 Curtis Pellatz In Review 02-14-22: Public Construction Plans for "Project Justify" have been added to the Session for review. GOAL 1: to determine if this current 60% Plan Set is "approvable", or acceptable for the purpose of allowing the Final Plat for Site "E" to record. GOAL 2: full plan review for construction of the required improvements, including the first priority of the sanitary sewer realignment.
2 3/21/2022 Curtis Pellatz Revisions Requested Steve and Marcie, We are still trying to get Scannell Properties to pay the required Plan Review Fees for PROJECT JUSTIFY. My concern is that you both have been working on revised designs even though you dont have the latest Plan Review Comments from Public Works as we wait for fee payment. I have uploaded the latest Staff comments for the Civil Site Work, Storm Report, and Public Construction Plans to the ShareFile website and send you separate links to the comments. Some of the comments may be outdate due to the recent meetings and conversations that have occurred. It is may hope that the City will soon see payment of the Plan Review Fees as Staff has invested a lot of time and effort to this point. At the same time, I would like to see the project continue to go forward. I hope this helps. After downloading the files, please feel free to contact me if you have any questions. Thanks, Curt Pellatz Senior Program Manager
3 4/25/2022 Curtis Pellatz Revisions Received Revisions recv'd and routed for review
4 5/18/2022 Curtis Pellatz Revisions Requested PRC3 routed to Project Engineer through ShareFile.
5 6/24/2022 Curtis Pellatz Revisions Received recv'd revised PC Plans. Added to open Session for Project Justify
6 7/15/2022 Curtis Pellatz Revisions Requested PRC4 to Engineer
7 7/28/2022 Curtis Pellatz Revisions Received Public Construction plans recv'd and routed for review. Civil Site Work and Storm Storm Report not received. I believe that the goal is to issue the Sanitary Sewer permits as soon as possible.
8 8/1/2022 Curtis Pellatz Info Received Recv'd Plan review Responses and Stormwater Report for PC Plans. Uploaded to open Bluebeam Session.
9 8/15/2022 Curtis Pellatz Revisions Requested PRC5 link emailed to Steve Ward.
10 9/6/2022 Curtis Pellatz Revisions Received Recv'd Storm Report and Responses. Routing Plans with Report to Staff.
11 9/21/2022 Curtis Pellatz Revisions Requested PRC6 Plan Review Comments email to Westech Engineering
12 9/29/2022 Curtis Pellatz Revisions Received Recv'd Revised PC Plans and responses to Plan Review Comments. Routed for Review
13 9/29/2022 Curtis Pellatz Revised Stormwater Report and responses to PRC6 recv'd and added to open Bluebeam Session.
14 12/4/2022 Curtis Pellatz Approved