Process Details

Description
Framing Inspection
Folder Number
21 115053 00 BP
Folder Details
4555 LIBERTY ROAD S Suite 350
Permit Type
Building Permit - Commercial
Scheduled Date
7/8/2022
Completed Date
8/12/2022
Assigned Staff
Inspector Structural

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 2/25/2022 Chad Cooper Inspected PARTIAL- APPROVED ALL INTERIOR PARTITION WALLS FOR COVER.
2 3/3/2022 Chad Cooper Inspected APPROVED NEW HEADER AT ROLL UP DOORS. APPROVED TEMP INFILL FOR BACKORDERD ROLL UP DOORS.
3 7/8/2022 Chad Cooper Inspected PARTIAL- APPROVED CEILING GRID AT KITCHEN.
4 8/12/2022 Matthew Smith Approved