Comment Number Scheduled Date Comment Date Staff Result Comment
1 11/2/2021 Curtis Pellatz In Review Recv'd Revised PH 2 Plans to match Phasing. Routed for Review and Approval.
2 11/23/2021 Curtis Pellatz Revisions Requested PRC9 Routed to MultiTech Engineering via ShareFile
3 1/24/2022 Curtis Pellatz Revisions Received Recv'd Revised Plans. Routed for Review
4 3/1/2022 Curtis Pellatz Revisions Requested PRC10 to MultiTech Engineering via ShareFile
5 4/13/2022 Curtis Pellatz Revisions Received Recv'd revised Plans
6 4/28/2022 Curtis Pellatz Revisions Received Recv'd Revised structural calculations for the Auburn Street Crossing. Routed Plans and Calculations for review .
7 5/6/2022 Curtis Pellatz Revisions Received Recv'd revised Structural Calcs. Routed for Review
8 5/10/2022 Curtis Pellatz Approved