Process Details

Description
DS Plan Review
Folder Number
21 110064 00 PC
Folder Details
PC_THE RESERVE AT BATTLE CREEK
Permit Type
Public Construction - PW - Subdivision
Scheduled Date
1/11/2022
Completed Date
1/17/2022
Assigned Staff
Curtis Pellatz

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 6/11/2021 Curtis Pellatz Recv'd first full PC Package and Plan Review Fees Paid. Routed for City Staff Review
2 7/7/2021 Curtis Pellatz Revisions Requested PRC1 Plan Review Comments uploaded to ShareFile and notified Josh Wells of Westech Engineering.
3 9/14/2021 Curtis Pellatz Revisions Received Recv'd Revised PC Plans, Storm Report, and Landscaping plans. Requested written responses to the PC Plans and Landscaping plans.
4 9/27/2021 Curtis Pellatz Revisions Requested PRC2 to Westech Engineering via ShareFile.
5 10/18/2021 Curtis Pellatz Revisions Received Recv'd Revised Plans and Reports. Routed for Review .
6 11/8/2021 Curtis Pellatz Revisions Received Recv'd Revised PC Plans, Storm Report, and new Design Exception Request (Storm). Added to Open Bluebeam Session.
7 11/24/2021 Curtis Pellatz Info Requested Per Don Whitehurst, He will be meeting with Josh Wells regarding the Street improvements and Storm Design. Possible Design Exception request need for Fee-In-Lieu option. Leaving Review Session open for Engineering.
8 12/3/2021 Curtis Pellatz Revisions Requested PRC3 routed to Josh Wells via ShareFile and email.
9 12/15/2021 Curtis Pellatz Revisions Received Recv'd Revised Plans and routed for review.
10 12/22/2021 Curtis Pellatz Info Received Recv'd Revised Sheets and Storm Report. Inserted new sheets into plan set and added complete set dated 20211222 to existing Bluebeam Session.
11 1/4/2022 Curtis Pellatz Revisions Requested Stormwater comments (PRC4) routed to Josh Wells through ShareFile.
12 1/10/2022 Curtis Pellatz Revisions Received Received Revised plans and Storm Report. Routed for Review
13 1/17/2022 Curtis Pellatz Approved