1 |
|
1/27/2021 |
Curtis Pellatz
|
In Review |
|
2 |
|
1/27/2021 |
Curtis Pellatz
|
Revisions Requested |
Please disregard the Bluebeam Review Session sent out this morning for the EAST PARK PH 3 project. I will be closing the Session while we sort out the phasing of the project. The plans submitted by MultiTech Engineering are out of phasing sequence of the approved Land Use Decision. Thank you,
Curt Pellatz
Senior Program Manager
City of Salem | Public Works Department
555 Liberty St SE, Suite 325, Salem OR 97301-3513
[email protected] | 503-588-6211
Facebook | Twitter |YouTube| CityofSalem.net |
3 |
|
5/7/2021 |
Curtis Pellatz
|
Revisions Requested |
To Date, No new information recv'd |
4 |
|
8/23/2021 |
Curtis Pellatz
|
Revisions Requested |
Plans dated 08-18 received and routed to Don Whitehurst for preliminary review. Don has provided comments. Teh comments (PRC1) have been provided to MultiTech Engineering via ShareFile. |
5 |
|
9/15/2021 |
Curtis Pellatz
|
In Review |
|
6 |
|
10/13/2021 |
Curtis Pellatz
|
Revisions Requested |
PRC2 Plan Review Comments provide to MultiTech Engineering via ShareFile. Notified Jeremy Grenz via email. |
7 |
|
11/5/2021 |
Curtis Pellatz
|
Revisions Received |
Complete Plans Recv'd and Routed for Review. |
8 |
|
11/16/2021 |
Curtis Pellatz
|
Approved |
|
9 |
|
4/18/2022 |
Curtis Pellatz
|
Approved |
Complete Construction Set Approved |