Process Details
- Description
- BAS Engineer Review
- Folder Number
- 20 114854 00 BP
- Folder Details
- 5669 COMMERCIAL STREET SE
- Permit Type
- Building Permit - Commercial
- Scheduled Date
- 12/17/2020
- Completed Date
- 12/17/2020
- Assigned Staff
- Ryan McGraw
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 10/2/2020 | Ryan McGraw | Info Requested | Info on sheet S3.1 is incomplete. Sent plan review letter asking for clarity of roof framing details. -RM | |
2 | 11/6/2020 | Ryan McGraw | Info Requested | Several structural issues lacking sufficient clarity of load path, no beam schedules that relate to the calcs, not enough design modeling or info to clearly illustrate that irregularities exist on this project. See plan review letter for a more detailed code reference summary. -RM | |
3 | 11/24/2020 | Ryan McGraw | Approved | A thoughtful plan review response was given and is approvable. Thank you LVVI. -RM | |
4 | 12/17/2020 | Ryan McGraw | Approved |