Process Details

Description
BAS Engineer Review
Folder Number
20 114854 00 BP
Folder Details
5669 COMMERCIAL STREET SE
Permit Type
Building Permit - Commercial
Scheduled Date
12/17/2020
Completed Date
12/17/2020
Assigned Staff
Ryan McGraw

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 10/2/2020 Ryan McGraw Info Requested Info on sheet S3.1 is incomplete. Sent plan review letter asking for clarity of roof framing details. -RM
2 11/6/2020 Ryan McGraw Info Requested Several structural issues lacking sufficient clarity of load path, no beam schedules that relate to the calcs, not enough design modeling or info to clearly illustrate that irregularities exist on this project. See plan review letter for a more detailed code reference summary. -RM
3 11/24/2020 Ryan McGraw Approved A thoughtful plan review response was given and is approvable. Thank you LVVI. -RM
4 12/17/2020 Ryan McGraw Approved