1 |
|
9/1/2020 |
Curtis Pellatz
|
In Review |
|
2 |
|
9/27/2020 |
Curtis Pellatz
|
Revisions Requested |
PRC1 to MultiTech Engineering via ShareFile. |
3 |
|
10/26/2020 |
Curtis Pellatz
|
Revisions Received |
Recv'd Complete Revisions in response to PRC1 including Storm Report and written responses to the storm report PRC1 comments. Still need plan review comment response for PRC1. Routing Plans and Storm report for Staff Review. |
4 |
|
11/9/2020 |
Curtis Pellatz
|
Info Received |
revised plans for Auburn Road recv'd by Don Whitehurst and added to Bluebeam Session |
5 |
|
11/18/2020 |
Curtis Pellatz
|
Revisions Requested |
PRC2 routed to MultiTech Engineering via ShareFile. |
6 |
|
12/4/2020 |
Curtis Pellatz
|
Revisions Received |
Revisions recv'd and routed for review |
7 |
|
12/10/2020 |
Curtis Pellatz
|
Info Received |
Recv'd Design Exception Request and added to Bluebeam Session. |
8 |
|
12/22/2020 |
Curtis Pellatz
|
Revisions Requested |
PRC3 to MultiTech Engineering via ShareFile |
9 |
|
1/15/2021 |
Curtis Pellatz
|
Revisions Received |
Recv'd revised ON-SITE plans and Storm Report. Routed for review. |
10 |
|
2/5/2021 |
Curtis Pellatz
|
Revisions Requested |
PRC4 to MultiTech Engineering via ShareFile |
11 |
|
2/10/2021 |
Curtis Pellatz
|
Revisions Received |
Revisions Received and Routed |
12 |
|
3/2/2021 |
Curtis Pellatz
|
Revisions Requested |
PRC5 to MultiTech Engineering via ShareFile |
13 |
|
3/8/2021 |
Curtis Pellatz
|
Revisions Received |
Revised Plans recv'd. Routed in Bluebeam |
14 |
|
4/2/2021 |
Curtis Pellatz
|
Approved |
|
15 |
|
5/10/2022 |
Curtis Pellatz
|
Approved |
Revised Phase 2 (On-Site) and Auburn Road |