1 |
|
10/21/2020 |
Matthew Smith |
Inspected |
FAPPROVED FREEZER PADS- FORMS REBAR AREA DRAINS |
2 |
|
1/8/2021 |
Matthew Smith |
Inspected |
APPROVED SLBA ON GRADE GRID LINE 4-7 FROM A-E |
3 |
|
1/15/2021 |
Chad Cooper |
Inspected |
APPROVED SLAB REBAR AND VAPOR BARRIER FOR FREEZER PAD, RAMP SECTION, AND SLAB FROM GRID LINES B - D ON LINE 1 - 5.
SEE PLAN FOR LOC. |
4 |
|
1/28/2021 |
Chad Cooper |
Inspected |
APPROVED REMAINDER OF SLAB MINUS THE FREEZER PADS. |
5 |
|
2/9/2021 |
Chad Cooper |
Inspected |
APPROVED FREEZER PAD #115 ON LINES D-F/ 2-4
APPROVED FREEZER PAD #117 ON LINES G-H/ 3-4 |
6 |
|
1/5/2022 |
Chad Cooper |
Approved |
APPROVED TO CLOSE FOLDER- CC 1/5/22 |