1 |
|
10/2/2020 |
Roberto Rios |
Inspected |
1. APPROVED COVERED PARKING/ STAIR #1
2. APPROVED TO POUR RECESSED SOG FOR RESTROOMS 2 AND 3 AND PATIO 300
SPECIAL INSPECTION REPORT VERIFIED
MAIN SOG AREAS 2 AND 3 INCOMPLETE / PLEASE RESCHEDULE |
2 |
|
10/7/2020 |
Matthew Smith |
Inspected |
APPROVED SOD NORTH HALF OF 2ND FLOOR AND ALL OF 3RD FLOOR |
3 |
|
11/2/2020 |
Matthew Smith |
Inspected |
APPROVED EXTERIOR FRAMING GIRD LINE E COL LINE 1-7 |
4 |
|
11/16/2020 |
Chad Cooper |
Inspected |
APPROVED A-LINE/ 1-8, NORTH END STAIRWELL, 3RD FLR BALCONY, AND GARAGE INTERIOR SOFFITS. |
5 |
|
12/4/2020 |
Matthew Smith |
Inspected |
APPROVED ALL EXTERIOR WALLS |
6 |
|
12/29/2020 |
Matthew Smith |
Inspected |
OK TO START 1 SIDING - 1ST -3RD FLOORS OTHER TRADE WORK NOT COMPLETE |
7 |
|
12/31/2020 |
Roberto Rios |
Inspected |
1. PARTIAL INSPECTION
TOP OF WALLS FRAMING APPROVED ALL FLOORS |
8 |
|
2/3/2021 |
Matthew Smith |
Inspected |
APPROVED HARD LIDS 3RD FLOOR RESTROOMS |
9 |
|
2/16/2021 |
Matthew Smith |
Inspected |
2ND FLOOR RESTROOMS SOFFITS |
10 |
|
3/9/2021 |
Matthew Smith |
Inspected |
ROOM 325 HARD LID |
11 |
|
3/15/2021 |
Matthew Smith |
Inspected |
APPROVED 1ST FLROOR RESTROOM HARD LIDS |
12 |
|
3/26/2021 |
Roberto Rios |
Inspected |
1. APPROVED PARKING STRUCTURE LID COVER/ 1ST FLOOR RMS 101.102.103,104 AND APPROVED PERIMERTER CEILING COVER ON THIRD FLOOR |
13 |
|
3/30/2021 |
Matthew Smith |
Inspected |
APPROVED 3RD FLOOR T-BAR GRID ALL AREAS EXCEPT SW LARGE ROOMS AND GLASS AREAS |
14 |
|
4/12/2021 |
Matthew Smith |
Inspected |
APPROVD LEVEL 1 AND PARTIAL LEVEL 3 AND STAIR 1 |
15 |
|
4/23/2021 |
Roberto Rios |
Inspected |
STAIR 2 LEVEL 3 DRY WALL GRID
OFFICE 224 CEILING GRID |
16 |
|
4/30/2021 |
Matthew Smith |
Approved |
REMAINING AREAS LEVELS 1&2 AND HIGH CEILING |