4 |
|
5/21/2020 |
Brandon Pike |
Info Requested |
Hi Hiro,
I just wanted to check in with you about the building permit for the Claxter project. I still see that the PLA survey has not been recorded with the County. Once that is recorded, I will be able to sign off on the building permit. However, there are a couple items to address first:
" Theres an area along the western portion of Building B which appears to be marked as gravel, but it will either need to be landscaped or paved as a walkway (see the attached screenshot, where I reference the pertinent section of code). I can just redline the plans to indicate this if you are OK with that, but I didnt know if you had other plans for this area that landscaping or a walkway would interfere with. Let me know either way.
" I still need to see a landscaping plan which shows the required plant units within the flag lot accessway, per Condition 8 of the land use decision.
Once these are addressed and the PLA survey is recorded, all of the Planning Divisions concerns at the building permit stage will be satisfied.
Let me know if you have questions.
Best,
Brandon Pike |