1 |
|
1/9/2020 |
Al Rossi
|
Info Requested |
Plan review letter sent |
2 |
|
2/14/2020 |
Mareva Massey
|
Info Received |
Secondary |
3 |
|
2/14/2020 |
NHINKLE |
Info Requested |
Secondary |
4 |
|
2/14/2020 |
NHINKLE |
Info Received |
Secondary |
5 |
|
2/24/2020 |
Al Rossi
|
Info Requested |
Still waiting on B&S plan review letter information request. 2/24/2020-AR |
6 |
|
2/25/2020 |
Mareva Massey
|
Info Received |
Secondary |
7 |
|
2/26/2020 |
Al Rossi
|
Info Requested |
Waiting on special inspection form to be submitted. 2/26/2020-AR |
8 |
|
5/5/2020 |
NHINKLE |
Info Received |
Secondary |
9 |
|
5/6/2020 |
Al Rossi
|
Info Requested |
Waiting on special inspection form to be submitted. 2/26/2020-AR, Called designer 5/6/2020 @2:00pm with follow up requesting special inspection form-AR |
10 |
|
6/1/2020 |
NHINKLE |
Info Received |
Secondary |
11 |
|
6/1/2020 |
Al Rossi
|
Info Requested |
Waiting on special inspection form to be submitted. 2/26/2020-AR, Called designer 5/6/2020 @2:00pm with follow up requesting special inspection form-AR |
12 |
|
6/2/2020 |
Rebai Tamerhoulet |
Approved |
|
13 |
|
9/23/2020 |
Rebai Tamerhoulet |
Approved |
|