Process Details

Description
DS Plan Review
Folder Number
19 123532 00 PC
Folder Details
PC-AFFINITY ESTATES_fka-Devon Estates PH 1
Permit Type
Public Construction - PW - zzArchive - SUB - Major Facilities
Scheduled Date
7/28/2021
Completed Date
9/27/2021
Assigned Staff
Curtis Pellatz

Process Comments

Comment Number Scheduled Date Comment Date Staff Result Comment
1 11/18/2019 Curtis Pellatz In Review
2 12/18/2019 Curtis Pellatz Met with Multi Tech to discuss the Plan Review Comments and the need for Design Exception Requests. Don Whitehurst in attendance.
3 12/19/2019 Curtis Pellatz Revisions Requested PRC1 to MultiTech Engineering via ShareFile
4 3/23/2020 Curtis Pellatz Revisions Requested To Date, No additional information recv'd
5 5/20/2020 Curtis Pellatz Revisions Received Recv'd Revised Plans and Storm Report. Requested written responses to PRC1. Routing Plans and Storm Report in Bluebeam
6 6/9/2020 Curtis Pellatz Curt: I have a meeting scheduled with Mark tomorrow at 9AM to review a few items. Id like to wait until after that meeting if we can. -Don
7 6/10/2020 Curtis Pellatz Revisions Requested PRC2 routed to MultiTech Engineering via ShareFile
8 9/16/2020 Curtis Pellatz Revisions Requested To Date, No new information recv'd
9 9/21/2020 Curtis Pellatz Revisions Received Recv'd revised PC Plans. Routed in Bluebeam
10 9/22/2020 Curtis Pellatz Revisions Received Curt, I apologize, I grabbed the incorrect set of plans, that was uploaded yesterday. I have reuploaded the correct set today. Thank you, Ed Humber
11 10/13/2020 Curtis Pellatz Revisions Requested PRC3 to MultiTech Engineering via ShareFile.
12 1/20/2021 Curtis Pellatz Revisions Requested No Action
13 4/15/2021 Curtis Pellatz Revisions Requested Hey Curt, I just uploaded the geotechnical report and revised plans to Sharefile, Matt is still finalizing his storm report and Mark is compiling his calc packet for the walls, Ill let you know when I have those uploaded. Thanks, Jeremy Grenz
14 4/21/2021 Curtis Pellatz Revisions Received Recv'd Storm Report and request from MultiTech to route the plans prior to Don's approval of the Final Grades of the Street Profiles.
15 5/12/2021 Curtis Pellatz Revisions Requested Plan Review Comments (PRC4) for the "AFFINITY ESTATES SUBDIVISION" project have been uploaded. Please follow the link. We highly recommend setting up a meeting to discuss the comments with City Staff. After reviewing the PRC4 Comments, please contact me to schedule a meeting. Curt Pellatz Senior Program Manager [email protected]
16 6/4/2021 Curtis Pellatz Recv'd revised plans and response summary. Requested a revised Storm Report and responses.
17 6/16/2021 Curtis Pellatz Revisions Received Recv'd Revisions. Routed for Review
18 7/13/2021 Curtis Pellatz Revisions Requested PRC5 to MultiTech Engineering via ShareFile
19 7/27/2021 Curtis Pellatz Revisions Received Recv'd Revised PC Plans and Reports. Routed for Review in Bluebeam
20 7/28/2021 Curtis Pellatz Approved
21 9/27/2021 Curtis Pellatz Approved Storm Pipe plans Approved.