Process Details
- Description
- DS Plan Review
- Folder Number
- 19 115996 00 PL
- Folder Details
- PL-NORTHSTAR I
- Permit Type
- Plats - Standard Subdivision
- Scheduled Date
- 9/16/2019
- Completed Date
- 9/20/2019
- Assigned Staff
- Curtis Pellatz
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 9/5/2019 | Curtis Pellatz | In Review | Hand Delivered to Maria Delaney. | |
2 | 9/16/2019 | Curtis Pellatz | Revisions Requested | City Surveyor Redline Comments dated 09-13-19 emailed to Robert Hammond at MultiTech Engineering. | |
3 | 9/16/2019 | Curtis Pellatz | In Review | Recv'd Revised Signed Mylar from Eric M. at front counter. Hand Delivered to Suzanne Keller. | |
4 | 9/20/2019 | Curtis Pellatz | Approved | Mylar has been signed by the Planning Administrator. |