1 |
3/25/2015 |
3/25/2015 |
PW Plan Reviewer
|
Info Received |
Morning Meeting 3-27-15 |
2 |
3/25/2015 |
3/26/2015 |
Robin Dalke
|
In Review |
PLA packet discussed in Thurs morning meeting and forwarded to Gerry. |
3 |
3/25/2015 |
3/30/2015 |
Robin Dalke
|
Revisions Requested |
review on hold until Record of Survey is received. See email in comment tab for more information. |
4 |
5/11/2015 |
4/16/2015 |
Robin Dalke
|
Revisions Requested |
recd electronic version of record of survey, see attached. Spoke with applicant's assistant about requested Planning changes and she said she will discuss with surveyor and get back to us. Waiting to route new survey for review until complete application (with requested revisions) is received. |
5 |
5/29/2015 |
4/28/2015 |
Robin Dalke
|
Revisions Received |
per email from Gerry, revised Record of Survey was recd (delivered to Gerry's office) on 4/16/15. See email in comment tab. |
6 |
4/16/2015 |
4/28/2015 |
Robin Dalke
|
Revisions Requested |
see attached redlines from Gerry |
7 |
6/10/2015 |
5/22/2015 |
Robin Dalke
|
Approved |
Revised PLA submitted directly to Gerry, sometime between 4/28/15 and 5/22/15. Recd approval letter via email, from Gerry. See attached. |