Development Permit Details

Number
17 119827 00 BP
Type
Building Permit - Commercial - New
Status
Finaled
Details
1805 WALN DRIVE SE
Description
BATTLE CREEK MEMORY CARE FACILITY: CONSTRUCT NEW SINGLE STORY 68 BED CARE CENTER

Person Details

Property Details

Street Address City State Zip Neighborhood Association Map
1805 WALN DR SE SALEM OR 97306

Info

Contractors' Construction Board #
181981

Valuation
5728160.00

Type of Construction
V A

Sq Ft - finished
35,800

Number of Floors
1

Zoning
CR, RETAIL COMMERCIAL

In Floodplain?
No

Action Details

Application Intake


    Info
  • Application Intake
    Status:
    Accept Plans
    Completed Date:
    10/6/2017
    Assigned Staff:
    Permit Technician
    View Details
  • Assign Bin Number
    Status:
    Complete
    View Details

Final B&S Inspections


    Info
  • Final PW Regulatory Review
    Status:
    Finaled
    Completed Date:
    10/24/2019
    Assigned Staff:
    PW Coordinator
    View Details
  • Final Fire Inspection
    Status:
    Finaled
    Completed Date:
    10/3/2019
    Assigned Staff:
    Deputy Fire Marshal
    View Details
  • Final Landscape Inspection
    Status:
    Finaled
    Completed Date:
    10/8/2019
    Assigned Staff:
    Aaron Panko
    View Details
  • Final Structural Inspection
    Status:
    Finaled
    Completed Date:
    9/30/2019
    Assigned Staff:
    Scott Morse
    View Details
  • Final Zoning Inspection
    Status:
    Finaled
    Completed Date:
    10/30/2019
    Assigned Staff:
    Aaron Panko
    View Details

Inspections-Building


    Info
  • Ufer Ground Inspection
    Status:
    Approved
    Completed Date:
    10/11/2018
    Assigned Staff:
    Leif Nelson
    View Details
  • Footing/Setback Inspection
    Status:
    Approved
    Completed Date:
    10/11/2018
    Assigned Staff:
    Inspector Structural
    View Details
  • Foundation Inspection
    Status:
    Approved
    Completed Date:
    9/20/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Grout/Rebar Inspection
    Status:
    Approved
    Completed Date:
    9/20/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Underfloor Framing Inspection
    Status:
    Approved
    Completed Date:
    9/20/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Shear Wall Inspection
    Status:
    Approved
    Completed Date:
    9/20/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Roof Nailing Inspection
    Status:
    Approved
    Completed Date:
    6/27/2019
    Assigned Staff:
    Chad Cooper
    View Details
  • Framing Inspection
    Status:
    Approved
    Completed Date:
    6/7/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Insulation Inspection
    Status:
    Approved
    Completed Date:
    9/20/2019
    Assigned Staff:
    Inspector Structural
    View Details
  • Sheetrock Nailing Inspection
    Status:
    Approved
    Completed Date:
    6/21/2019
    Assigned Staff:
    Chad Cooper
    View Details
  • Masonry Fireplace Inspection
    Status:
    Open
    Assigned Staff:
    Inspector Structural
  • Blocking/Manuf. Dwelling Setup Insp.
    Status:
    Open
    Assigned Staff:
    Inspector Structural

Plan Review