Development Permit Details
17 107268 00 PC
- Number
- 17 107268 00 PC
- Type
- Public Construction - zzArchive - SUB - Major Facilities - Water/Sewer/Street/Storm
- Status
- Completed
- Details
- FAIRVIEW ADDITION WEST PH 3 PN 716733
- Description
- Phase 3 of the Fairview Addition West project. 17-Lots
Person Details
WESTECH ENGINEERING INC
- Roles
- Engineer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
RAYMOND ENGEL
- Roles
- Engineer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
SALEM ROAD AND DRIVEWAY COMPANY
- Roles
- Contractor
- Address
-
PO BOX 12927
SALEM OR 97309-0927
Property Details
Action Details
Application Intake
-
Assign Bin Number
- Status:
- Open
- Assigned Staff:
- PW Coordinator
-
Make Ready To Issue (PW)
- Status:
- Approved
- Completed Date:
- 6/29/2017
- Assigned Staff:
- Lyle Misbach
- View Details
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 6/21/2017
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 6/29/2017
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Fire Review
- Status:
- Approved
- Completed Date:
- 4/3/2017
- Assigned Staff:
- Fire Plan Review
- View Details
Info
PW Inspections
-
As-Built Review
- Status:
- Complete
- Completed Date:
- 5/2/2019
- Assigned Staff:
- PW Engineering
- View Details
-
Acceptance
- Status:
- Accepted
- Completed Date:
- 5/31/2018
- Assigned Staff:
- PW Engineering
- View Details
-
10-month TV Inspection
- Status:
- Approved
- Completed Date:
- 5/2/2019
- Assigned Staff:
- PW Sewer
- View Details
-
ADA Ramps
- Status:
- Approved
- Completed Date:
- 6/1/2018
- Assigned Staff:
- PW Inspector
- View Details
-
10 month warranty inspection
- Status:
- Approved
- Completed Date:
- 3/31/2019
- Assigned Staff:
- PW Inspector
- View Details
-
Sewer TV Inspection
- Status:
- Complete
- Completed Date:
- 4/29/2019
- Assigned Staff:
- PW Sewer
- View Details
-
Storm TV Inspection
- Status:
- Complete
- Completed Date:
- 4/29/2019
- Assigned Staff:
- PW Sewer
- View Details
-
Chlorination <=12"
- Status:
- Completed by City
- Completed Date:
- 11/22/2017
- Assigned Staff:
- Donald Lovas
- View Details
-
Erosion Control Inspection
- Status:
- Approved
- Completed Date:
- 3/8/2018
- Assigned Staff:
- Michael Marr
- View Details
Info