Development Permit Details
25 104315 00 CO
Permit- Number
- 25 104315 00 CO
- Type
- Commercial Permit - DS - Multi Family - New
- Status
- Permit Issued
- Details
- CO - SCHURMAN COTTAGES - 2512 GILBERT STREET S
- Description
- CIVIL SITE WORK FOR 11 NEW COTTAGE CLUSTER UNITS
Person Details
CLUTCH INDUSTRIES
- Roles
- Bill To (Bill/Receipt), Contractor, Paid By
- Address
-
360 BELMONT ST NE
SALEM OR 97301
SCHURMAN COTTAGES LLC
- Roles
- Responsible Utility Billing Contact, Owner
- Address
-
PO BOX 3230
SALEM OR 97302
GENE BOLANTE
- Roles
- Applicant, Contact
- Address
-
PO BOX 5456
SALEM OR 97301
JOSH WELLS
- Roles
- Contact, Designer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
KIP PATTERSON
- Roles
- Contact
- Address
-
793 LAKEFAIR PL N
KEIZER OR 97303
Property Details
Info
- PSI
- 105
- Water Service Level
- S1
- USGS Elevation
- 200
- Install Domestic Water Meter?
- New
- Install Domestic Water Service Line
- New
- Domestic Water Meter Type
- Disk
- Domestic Water Service Line Size
- 2-inch
- Domestic Water Meter Size
- 1.5-inch
- In Urban Service Area?
- Yes
- County Name
- Marion
- Subject to SDF?
- Yes
- Permits Required?
- Yes
- Proposed Developed Area
- .58
- Jurisdiction
- Salem
- Special Conditions
- Contractor to follow all State and Federal regulations. Separate mechanical, electrical, plumbing, and fire systems permits are required for on-site/private utility installation (please contact Building & Safety at 503-588-6256). Any work performed within City of Salem public right-of-way requires a separate "Work in ROW" permit (please contact Ron Adkins or Van Tran at 503-588-6211).
- Geo Review Req'd?
- No
- Erosion Control Permit Req'd?
- City Permit
- Adjacent to Waterway/Wetlands?
- No
- Excavation/Fill Permit Req'd
- No
- Install Irrigation Water Meter?
- No
- Install Irrigation Water Service Line
- No
- Irrigation Water Meter Type
- Disk
- Driveway Req'd
- New
- Driveway Width
- 24
- Driveway Location
- GILBERT ST S
- Driveway #2 Req'd
- None
- Driveway Closure Req'd
- No
- Driveway #2 Closure Req'd
- No
- Sidewalk Req'd?
- New
- Sidewalk Width
- 5
- Sidewalk Length
- 131
- Sidewalk Street Name
- GILBERT ST
- Sidewalk Location
- Property Line
- Sidewalk #2 Req'd?
- None
- Lane Closure Required
- None
- Storm?
- Connect
- Length of Storm Pipe
- 33
- Storm Location
- 10-inch SD lateral, 4-inch SD lateral, connects to new public SDMH and/or public storm main constructed under 25-110332-PCO. GSI facilities on-site, see plans for details and locations.
- Storm Disconnect
- Yes
- Street Opening Required?
- No
- Storm Tap Type
- None
- Sewer Tap Type
- None
- Sewer?
- Connection - Inside City
- Length of Sewer Pipe
- 35
- Sewer Location
- 6-inch SS lateral, connects to new public SSMH and public sewer main constructed under 25-110332-PCO.
- Is Floodplain Development Required?
- N/A
- Elevation Certificate Req'd?
- No
- Latitude/Longitude
- Null
- Horizontal Datum
- NAD 1927
- NFIP Community Name & Community Number
- Salem, City of & 410167
- State
- Oregon
- Firm Index Date
- 1/2/2003
- Base Flood Elevation Source
- FIRM
- Elevation Datum
- NGVD 1929
- Is this CBRS or OPA?
- No
- ROW Dedication Req'd?
- Yes
- ROW Dedication Description
- ROW Dedication along Gilbert Street S & Schurman Drive S
- Number of Dwelling Units
- 11
- Commercial Vehicle Trips
- 72
- New Impervious Area (sq ft)
- 17525
Action Details
Agreements
-
ROW Dedication
- Status:
- Open
- Assigned Staff:
- Matt Olney
-
PSFA
- Status:
- In Review
- Assigned Staff:
- Jason Valyou
- View Details
Info
Final B&S Inspections
-
Regulatory Final
- Status:
- Open
- Assigned Staff:
- PW Coordinator
Info
Inspections-Planning
-
Protected Tree Inspection
- Status:
- Inspected
- Assigned Staff:
- Michael Conkey
- View Details
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 6/12/2025
- Assigned Staff:
- Matt Olney
- View Details
-
PW Make Ready To Issue
- Status:
- Ready to Issue
- Completed Date:
- 6/12/2025
- Assigned Staff:
- PW Coordinator
- View Details
-
DS Landscape Review
- Status:
- Closed
- Completed Date:
- 6/12/2025
- Assigned Staff:
- Matt Olney
- View Details
Info
PW Environmental Services
-
Environmental Services Inspection
- Status:
- Open
- Assigned Staff:
- Environmental Services
Info
PW Finals
-
Final Field Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
Info
PW Inspections
-
Sewer Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Storm Disconnect Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Storm Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Driveway Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Sidewalk Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Erosion Control Inspection
- Status:
- Inspected
- Assigned Staff:
- PW Inspector
- View Details
-
ADA Ramps
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Stormwater Facility Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Stormwater Facility Landscaping Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Street Trees
- Status:
- Open
- Assigned Staff:
- PW Inspector
Info
PW Water Inspections
-
Meter Installation
- Status:
- Open
- Assigned Staff:
- Devin Newstrand
-
Water Tap Installation
- Status:
- Open
- Assigned Staff:
- Devin Newstrand
Info
PW Water Quality & Treatment Inspections
-
PW Backflow Device Inspection
- Status:
- Open
- Assigned Staff:
- Scott Ruyle
Info